Massive Attack at The Downs

A Serious Stages Case Studies

Project Info:

  • Dates: 3-3 September 2016
  • Duration: 2 weeks
  • Location: The Downs, Bristol
Share:

We have worked with Team Love for several years on other Bristol shows, and we were once again proud to support our local client. With a very quick turnaround on kit, we opted for our 19m Supernova Knee Roof which consisted of five 3.6m bays and a cantilever roof to give added weather protection, which was much needed on the day. Covered extensions were added stage left and right to house monitors and technical equipment, along with a 14.4m x 2.4m loading dock, ramps and steps. The speakers were hung from our free standing Asteroid PA tower systems, which flanked the stage and offered 2000kg of load capacity. We also supplied a 4.8m x 4.8m front of house tower, decked on three levels to house lighting and sound, along with a 12m x 7.2m assisted viewing platform to ensure optimum views for the whole audience.